265 Strand
London. WC2R

Overview.

The 265 Strand project was carried out over 2 phases over a 6 month period, Phase 1 to remove all previous tenant installed fixtures, fittings and partitioning over and Phase 2 was to remove the landlord ceilings, perimeter linings and raised floor installations, both phases carried out to Lower Ground to 6th floor level.

The second phase of works included the isolation and decommissioning of all MEP services back to incoming plant rooms within the Lower Ground level and to remove all redundant plant to the 7th and 8th floor level plant rooms.

Again logistics planning and management were the key factor for removal of debris from the site which was all carried out along the side road of the building that was also shared with the London School of Economics, used for both pedestrians and vehicular access on a daily basis. Attention was focused on  liaising with the College building management and to manage and control the pedestrians and deliveries whilst loading was carried out.

Contract value
£1,040,000
Client
265 Strand Property S.a.r.l
Employment Status
Principal Contractor
Client Contract Period
6 months
Architects
Bluebottle
Contract Admin/PQS
Hollis Global Ltd / Core Five LLP